Province rejects revised Green Line plan, says funding to be withheld
Even though hundreds of millions of dollars have already been spent on preparatory work, Dreeshen said ‘throwing good money after bad is simply not an option for our government’
In a scathing letter to Mayor Jyoti Gondek, the province has ripped Calgary’s shrunken Green Line LRT plan, saying it won’t pay for the latest version.
Transportation and Economic Corridors Minister Devin Dreeshen also said the project will undergo a third party review with an eye to an expanded scope using the project’s current budget.
In the Sept. 3 letter obtained by Postmedia, Dreeshen calls the revised concept of the southeast-to-downtown LRT plan a wasteful disaster and states the province can’t in good conscience follow through with its $1.53-billion funding share.
“The Green Line is fast becoming a multi-billion-dollar boondoggle that will serve very few Calgarians,” wrote Dreeshen.
“This is unacceptable and our government is unable to support or provide funding for this revised Green Line Stage 1 scope as presented in the city’s most recent business case.”
Even though hundreds of millions of dollars have already been spent on preparatory work, he said “throwing good money after bad is simply not an option for our government.”
The minister expressed concern over the plan’s projected 40 per cent reduction in ridership compared to a previous larger version while its expected price tag has risen by 14 per cent.
But Dreeshen expressed some sympathy for the position of the current city council while taking a swipe at Gondek’s mayoral predecessor, newly minted Alberta NDP Leader Naheed Nenshi.
“We recognize … the untenable position you’ve been placed in by the former mayor and his utter failure to competently oversee the planning, design and implementation of a cost-effective transit plan that could have served hundreds of thousands of Calgarians in the city’s southern and northern communities,” Dreeshen wrote.
He went on to say the province is willing to contract with an independent third party to supply the province and city with an alternative costed proposal to integrate the Green Line with the Red and Blue Lines running along downtown 7th Avenue and to a future Grand Central Station in the east end entertainment district, to be anchored by a new events centre.
“And then continue above ground to, at least, the community of Shepard and hopefully beyond using the current budget used in your most recent business case.”
Dreeshen said the province would also work to include in that plan an above-ground or elevated link between 7th Avenue and Eau Claire.
Amid inflationary pressures, council voted for truncated Green Line plan
The letter follows one sent to city officials by Dreeshen last May that warned provincial funding for the project is dependent on the Green Line integrating with his government’s rail master plan.
In a 10-5 vote on July 30, a city council facing inflationary pressures opted for a truncated alignment for the Green Line project that removes five stations from the original vision, while deferring another.
The reconfigured first phase will see a train line with just seven stops extending from Eau Claire to Lynnwood/Millican in the southeast. And due to inflationary pressures, the project is now expected to cost nearly $6.3 billion — $705 million more than previously budgeted.
The shortened alignment takes out previously planned stops in Ogden, South Hill, Quarry Park, Douglas Glen and Shepard. Construction of those stations will be contingent on the city securing more funding from higher orders of government in the future.
City council members say they opted for the smaller scope of Phase 1 in an effort to get shovels in the ground and avoid further expensive delays.
https://pgaa.ca/wp-content/uploads/2024/09/0801-green-line-redo.png
Green Line mired in politics
Dreeshen in his letter Tuesday makes no mention of providing additional funding to enable the Green Line to reach Shepard or beyond but speaks of “working cooperatively with the city in determining next steps.”
The LRT line has become not only a policy hot potato in Calgary but has once again entered the provincial political realm with the UCP pinning the blame for its woes on Nenshi, while the NDP leader accuses the government, under then-premier Jason Kenney, of two years of foot-dragging on its support, driving up costs.
“They see this as an opportunity to score cheap political points on me,” Nenshi told Postmedia in late-July.
“They think that’s worth telling the people of Calgary, ‘We’re not investing in rapid transit for you, we’re more focused on our own train dreams outside of the city.’”
Kenney has furiously denied those accusations, insisting the province did three months of due diligence and that the city is at fault for its failure to launch the project efficiently.
— With files from Scott Strasser and Don Braid